92 million dollars over cost on a 4.1 million dollar project is not incompetence and mismanagement.
Doubling the cost of a project should have triggered reviews or an audit. 23x’ing the cost of a project is either corruption, or such gross negligence with public funds as to be criminal all on its own.
The 4.1m was the budget for the front-end. The back-end changes were initially budgeted as 31m but tripled in cost as the project dragged on and contracts needed to be extended.
92 million dollars over cost on a 4.1 million dollar project is not incompetence and mismanagement.
Doubling the cost of a project should have triggered reviews or an audit. 23x’ing the cost of a project is either corruption, or such gross negligence with public funds as to be criminal all on its own.
The 4.1m was the budget for the front-end. The back-end changes were initially budgeted as 31m but tripled in cost as the project dragged on and contracts needed to be extended.